Rising industry of Interior Design & Development
We are glad to have worked with the leading companies.
In Mumbai as well as India, providing them with the best we can.
Client brands




























Also worked with



These brands appear on the firm's client wall but not in the fifty-project register, so no project details are claimed for them.
01 / The record
Our completed projects
50 projects, 9,25,407 sq ft, 12 cities, 2008-09 to 2018-19.
Showing 50 of 50 projects · 9,25,407 sq ft
| Scope | Architect | Duration | |||||
|---|---|---|---|---|---|---|---|
| 01 | Fullerton Credit | Civil & Interior | Andheri, Mumbai | Karim Noorani & Co. | 90 days | 2008-09 | 20,000 sq ft |
| 02 | Marriott Hotels India | Turnkey | Juhu, Mumbai | Design-build | 60 days | 2008-09 | 4,659 sq ft |
| 03 | Essel Sports | Civil & MEP | Lower Parel, Mumbai | IDA Architects | 30 days | 2008-09 | 683 sq ft |
| 04 | Zee Entertainment Enterprises | Civil & Interior | Worli, Mumbai | Barve Associates | 70 days | 2008-09 | 3,000 sq ft |
| 05 | Zee Entertainment Enterprises | Civil & Interior | Versova, Mumbai | IDA Architects | 20 days | 2008-09 | 5,000 sq ft |
| 06 | Pandhe Infracons | Civil & Interior | Worli, Mumbai | Ushma Shah Interior Design | 70 days | 2009-10 | 3,500 sq ft |
| 07 | Zee News | Civil & Interior | Worli, Mumbai | Barve Associates | 50 days | 2009-10 | 10,000 sq ft |
| 08 | Ohum Healthcare Solutions | Civil & Interior | Viman Nagar, Pune | Ethique Architects | 120 days | 2011-12 | 5,400 sq ft |
| 09 | Hiranandani Group | Civil & Interior | Powai, Mumbai | Architect Hafeez Contractor | 90 days | 2011-12 | 2,400 sq ft |
| 10 | Hiranandani Group | Civil & Interior | Powai, Mumbai | Architect Hafeez Contractor | 360 days | 2011-12 | 9,000 sq ft |
| 11 | DNA | Civil & MEP | Lower Parel, Mumbai | Ethique Architects | 60 days | 2012-13 | 18,000 sq ft |
| 12 | Omega Associate Olympia | Civil & Interior | Powai, Mumbai | Desine Center Architects | 40 days | 2012-13 | 8,000 sq ft |
| 13 | Hiranandani Group | Civil & Interior | Chandivali, Mumbai | Desine Center Architects | 45 days | 2012-13 | 57,360 sq ft |
| 14 | Hiranandani Group | Civil & Interior | Chandivali, Mumbai | Desine Center Architects | 45 days | 2012-13 | 45,455 sq ft |
| 15 | Pinkberry | Civil & Interior | Bandra (Pali Naka), Mumbai | Zebra Project FZE | 40 days | 2013-14 | 600 sq ft |
| 16 | RSC Office | Civil & Interior | Lower Parel, Mumbai | Design-build | 90 days | 2013-14 | 3,750 sq ft |
| 17 | Hard Rock Cafe | Civil & Interior | Andheri, Mumbai | Khosla Associates | 90 days | 2013-14 | 7,500 sq ft |
| 18 | Mai-Tai Restaurants | Civil & Interior | Lower Parel, Mumbai | The Architects (Ashish Kamble) | 90 days | 2013-14 | 2,500 sq ft |
| 19 | Hard Rock Cafe | Civil & Interior | Gurgaon | Bobby Mukherji & Associates | 90 days | 2013-14 | 7,000 sq ft |
| 20 | Hotel Rodas & Parabola Restaurant | Civil & Interior | Powai, Mumbai | Desine Center Architects | 90 days | 2013-14 | 42,000 sq ft |
| 21 | Sahara Group | Civil & Interior | Bandra Kurla Complex, Mumbai | Architect Hafeez Contractor | 150 days | 2013-14 | 1,41,000 sq ft |
| 22 | Nomura | Civil & Interior | Powai, Mumbai | Desine Center Architects | 45 days | 2013-14 | 5,000 sq ft |
| 23 | Bayer CropScience | Civil & Interior | Thane (Kolshet Road), Thane | Architect Hafeez Contractor | 90 days | 2014-15 | 75,000 sq ft |
| 24 | AudienceScience India | Civil & MEP | Wanowrie, Pune | Ethique Architects | 90 days | 2014-15 | 6,000 sq ft |
| 25 | Heckyl Technology | Civil & Interior | Powai, Mumbai | Karma Designs (Poorna Mainkar) | 90 days | 2014-15 | 2,800 sq ft |
| 26 | Music Broadcast (Radio City) | Turnkey | Bandra, Mumbai | Design-build | 90 days | 2014-15 | 1,700 sq ft |
| 27 | Stryker India | Civil & MEP | Kanjurmarg, Mumbai | Ethique Architects | 60 days | 2014-15 | 2,000 sq ft |
| 28 | Huntsman International | Civil & Interior | Chandivali, Mumbai | Concept Architectural Services | 90 days | 2013-14 | 12,000 sq ft |
| 29 | Hiranandani Group | Civil & Interior | Thane (Godbunder Road), Thane | Desine Center Architects | 150 days | 2013-14 | 2,00,000 sq ft |
| 30 | Hiranandani Group | Civil & Interior | Sahar, Andheri, Mumbai | Pushkar Consultants | 180 days | 2013-14 | — |
| 31 | Private residence (client not named) | Civil & Interior | Khar, Mumbai | Nisar Ahmed & Associates | 120 days | 2014-15 | 5,000 sq ft |
| 32 | Indiabulls Constructions | Civil & Interior | Lower Parel, Mumbai | Fab Interiors | 40 days | 2014-15 | 18,000 sq ft |
| 33 | State Street Syntel Services | Civil & Interior | Airoli, Navi Mumbai | Vijay Punjabi Consultants Pvt. Ltd. | 150 days | 2014-15 | 75,000 sq ft |
| 34 | Crompton Greaves | Civil & MEP | Kanjurmarg, Mumbai | Studio3 Architects | 45 days | 2014-15 | 15,000 sq ft |
| 35 | iGate Global Solutions | Civil & Interior | Airoli, Navi Mumbai | DSP Architectes | 120 days | 2014-15 | 25,000 sq ft |
| 36 | Tata Consultancy Services (TCS) | Turnkey | Chennai | P.D. Design Studio | 120 days | 2014-15 | 15,000 sq ft |
| 37 | Tata Consultancy Services (TCS) | Turnkey | Goa | P.D. Design Studio | 120 days | 2014-15 | 6,000 sq ft |
| 38 | Tata Consultancy Services (TCS) | Civil & Interior | Thane (Godbunder Road), Thane | Desine Center Architects | 150 days | 2014-15 | 25,000 sq ft |
| 39 | Tata Consultancy Services (TCS) | Civil & Interior | Chandigarh | P.D. Design Studio | 45 days | 2015-16 | 5,000 sq ft |
| 40 | WNS Global Services | Civil & Interior | Vikhroli, Mumbai | Work Sphere | 60 days | 2015-16 | 1,000 sq ft |
| 41 | Indiabulls Constructions | Civil & Interior | Lower Parel, Mumbai | Anupam De Associates | 150 days | 2015-16 | 10,000 sq ft |
| 42 | Varaha Legal | MEP | Mulund, Mumbai | Setal Joshi | 2 months | 2015-16 | 1,000 sq ft |
| 43 | Pizza Express | Civil & Interior | Kurla, Mumbai | Cromed Design Studio | 3 months | 2017-18 | 3,400 sq ft |
| 44 | Tata Consultancy Services (TCS) | Civil & Interior | Nashik | P.D. Design Studio | 54 days | 2017-18 | 7,000 sq ft |
| 45 | Delhi Duty Free Services | Civil & Interior | New Delhi | KGD Architecture | 40 days | 2017-18 | 400 sq ft |
| 46 | Music Broadcast (Radio City) | Civil & Interior | Jalandhar | Area Consultant | 45 days | 2017-18 | 2,000 sq ft |
| 47 | Music Broadcast (Radio City) | Civil & Interior | Gorakhpur | Area Consultant | 45 days | 2017-18 | 2,000 sq ft |
| 48 | Voltas | Civil & Interior | Mumbai | Vijay Punjabi Consultants Pvt. Ltd. | 3 months | 2017-18 | — |
| 49 | Voltas | Civil & Interior | Mumbai | Vijay Punjabi Consultants Pvt. Ltd. | 3 months | 2018-19 | 6,500 sq ft |
| 50 | Bharat Infra | Civil & Interior | Vidyavihar, Mumbai | Sujit Patel | 3 months | 2018-19 | 1,800 sq ft |